Postponing Parkhill Road resurfacing pending short-term improvement options

Full Resolution Text

That the report be received for information, and that, Whereas the segment of Parkhill Road From Medical Drive to Wallis Drive is due for life-cycle maintenance under the pavement preservation program and the Transportation Master Plan has identified this corridor for future study to determine long-term improvements: On approval of Budget Item #22-020, that staff postpone the resurfacing of the segment of Parkhill Road from Medical Drive to Wallis Drive, and report back during the 2025 Budget on the potential short-term improvements that can be included with a future resurfacing project, with consideration for the long-term improvements required for the corridor, and that $125,000 be transferred from Capital Project #22-020 to a new capital project to initiate this work.